Right – we have quite a lot to do between now and Monday 15th September in order to move to the next stage of our redevelopment:
- build a new door
- install furniture in the new IT room on Level 4
- relocate our library offices into the new IT room on Level 4
- close down the current entrance
- set up a temporary entrance and issue desk
You can imagine that this may have a disruptive effect on the Library Services, and also on the Library as a quite place to work.
But how will it affect you?
- Saturday 6th September: we’ll be building a door near the books. This will cause a bit of noise and disruption
- Monday 8th & Tuesday 9th September: furniture for the new IT Room on Level 4 will be delivered and installed. Watch out for delivery men.
- Tuesday 9th – Friday 12th: Library staff will be moving offices – this might mean that we’re a bit distracted, and there might be some noise as we dismantle our current office – please bear with us!
- Friday 12th September: We’ll be closing the current entrance to the library, and opening a new temporary entrance which will be in operation till mid-November. Look out for the signs directing you to the new entrance.